74、Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider ( )。
A、crashing the schedule
B、performing resource leveling
C、conducting reverse resource allocation scheduling
D、utilizing the critical chair resources
分析:
由于团队成员之间有冲突使得项目进度滞后。要解决冲突使项目赶上进度,你应该(74)
A:赶工;B:进行资源平衡;C:实施反向资源分配;D:使用关键资源。
参考答案:B