cverification is ( )。
A、review the performance of an installed software module
B、managing changes to the project schedule
C、decomposing the WBS to a work package level
D、performing a benefit/cost analysis to determine if we should proceed with the project
分析:
下列选项属于范围确认的是(73)
A:检查已安装的软件模块的性能 B:管理进度变更
C:分解WBS到工作包级别 D:进行收益/成本分析来确定项目是否继续进行
排除法!
参考答案:A