The project budget has been finalized. Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.
A. Contingency reserve B. Project profit
C. Management reserve D. Special fund
分析:
项目预算已经确定后,发现了一些不在项目预算或项目范围内的额外的工作。(74)能提供资金来应对这些工作。
A 应急储备金 B 项目利润
C 管理储备金 D 特别基金
参考答案:C