Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73) .
A. project management plan B. project baseline
C. risk response plan D. risk baseline
分析:
管理和记录风险对于项目计划过程十分重要。在定义重要风险时,涉及相关参数和假设,计划风险的应对和费用,这些细节包含在(73)中。
A 项目管理计划 B 项目基线
C 风险应对计划 D 风险基线
参考答案:C