试题74-命-技-N.ZJ.00.p000-22.0All of followings should be done by the project manager during project control except (74).A. Determine that a change has occurredB. Ensure that a change is agreedC. Make sure all changes are approved by managementD. Manage chan
<尚大教育,教育至上,人才为大:sdedu.cc>

 

试题74-命-技-N.ZJ.00.p000-22.0

All of followings should be done by the project manager during project control except (74).

A. Determine that a change has occurred

B. Ensure that a change is agreed

C. Make sure all changes are approved by management

D. Manage changes as they occur

分析:

下列中,(74)不是项目经理在项目控制过程要完成的工作

A、确定变更已经发生

B、确保变更被同意

C、确保所有变更均被管理人员批准

D、变更发生是对其进行管理

参考答案:B、C

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:试题73-命-技-N.ZJ.00.p000-22.0
下一篇:试题75-命-技-N.ZJ.00.p000-22.0
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章