试题72-命-管-N.ZJ.00.p000-1.00-
来源: 作者: 时间;2017-11-13 11:26:23 点击数: 尚大软考交流群:376154208
试题72-命-管-N.ZJ.00.p000-1.00-A proj ect manager is called to an informal meeting with the customer and a problem is raised. Thisproblem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeti
<尚大教育,教育至上,人才为大:sdedu.cc>

 

试题72---N.ZJ.00.p000-1.00-

A proj ect manager is called to an informal meeting with the customer and a problem is raised. Thisproblem has major implications for the project manager's company but the customer wants to pursue a solution at the meeting.The project manager should (72)

Atell the customer that he will not address any problems becausethis is only an information exchangemeetmg

Bell the customer that the problem is not sufficiently defined to determine the appropriate action

Collect as much information on the problem without committing his company to a solution

Dgive the customer a range of solutions that might be acceptable to his Company

【正确答案】C

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:试题71-命-管-N.ZJ.00.p000-1.00-
下一篇:试题73-命-管-N.ZJ.00.p000-1.00-
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章