73、74、Requirements management is the process of (73),analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome(product or service)should conform. 
(73)	A. communicating 						B. collecting 
		C. filing 								D. documenting 
(74)	A. persistent 							B. continuing 
		C. permanent 							D. continuous
分析:
需求管理是对需求进行(73)、分析、跟踪、排序、确认,进行变更控制并与项目干系人进行沟通的一系列过程。它是作为一个(74)过程贯穿项目始终。项目成果(产品或服务)应符合项目需求。
(73)A、沟通			B、收集				C、归档				D、记录
(74)A、持续的			B、连续的			C、永久性的			D、连续的
参考答案:(73)B、(74)ABD