73、74、Requirements management is the process of (73),analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome(product or service)should conform.
(73) A. communicating B. collecting
C. filing D. documenting
(74) A. persistent B. continuing
C. permanent D. continuous
分析:
需求管理是对需求进行(73)、分析、跟踪、排序、确认,进行变更控制并与项目干系人进行沟通的一系列过程。它是作为一个(74)过程贯穿项目始终。项目成果(产品或服务)应符合项目需求。
(73)A、沟通 B、收集 C、归档 D、记录
(74)A、持续的 B、连续的 C、永久性的 D、连续的
参考答案:(73)B、(74)ABD