【1211高项】试题75-命-技-N.ZJ.00.p000-9.00-75、The most crucial time for project risk assessment is ( ).A. when a problem surfaces B. during the planning phase C. during the close-out phase D. after the project schedule has been published参考答案:B
<尚大教育,教育至上,人才为大:sdedu.cc>
【1211高项】试题75-命-技-N.ZJ.00.p000-9.00-
75、The most crucial time for project risk assessment is ( ).
A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published
参考答案:B