【英语专题 】【1211高项】试题73-命-技-N.ZJ.00.p000-9.00- 73、The communication
来源: 作者: 时间;2017-11-01 15:48:25 点击数: 尚大软考交流群:376154208
【1211高项】试题73-命-技-N.ZJ.00.p000-9.00-73、The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan, ( )is false.A. The communication manag
<尚大教育,教育至上,人才为大:sdedu.cc>

 

1211高项】试题73-命-技-N.ZJ.00.p000-9.00-

73、The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan,   is false.

A. The communication management plan is contained in, or is a subsidiary plan of, the project management plan

B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project      

C. The communication management plan organize and summarize the information gathered, and present the results of any analysis as compared to the performance measurement baseline

D. The communication management plan can include guidelines for project status meetings, project team meetings, e-meetings, and e-mails

参考答案:C

 

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:【英语专题 】【1211高项】试题72-命-技-N.ZJ.00.p000-9.00- 72、A data warehouse is
下一篇:【英语专题 】【1211高项】试题74-命-技-N.ZJ.00.p000-9.00- 74、Stakeholder management
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章