【1011高项】试题75-命-技-N.ZJ.00.p000-9.00-WBS.工作包75、Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource B.individual work load C.work milestone
<尚大教育,教育至上,人才为大:sdedu.cc>
【1011高项】试题75-命-技-N.ZJ.00.p000-9.00-WBS.工作包
75、Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.
A.independent resource B.individual work load
C.work milestone D.work package
C类(75)D ……直到分解到“工作包”为止