74、The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().
A.balance engineering B.fast-tracking
C.leveling D.crashing
尚大教育-分析:
客户要求你的项目比计划提前6个月完成,你认为这个目标可以通过重叠项目活动来达到。这种方法被称为()。
A、平衡技术 B、快速跟进 C、分级 D、赶工
尚大教育-参考答案:B