73、The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.
A. Schedule and cost B. Organization structuring
C. Management coordination D. Quality of work
分析:
73、工作分解结构(WBS)已被广泛应用于管理软件开发项目中,()一般不通过WBS验证。
A.进度和成本 B.组织结构
C.管理协调 D.工作质量
参考答案:D