【1411中项】试题75-命-技-N.ZJ.00.p000-22.0
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the().
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
分析:
整体变更控制贯穿于项目始终,并由()最终负责
A、变更控制委员会
B、项目管理办公室
C、项目经理
D、配置管理办公室
参考答案:A