In project management, a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74), budget and duration, linked by dependencies and scheduled events.
(73)A. schedule B. activity C. Plan D contractor
(74)A. finding B. balance C. allocation D. distribution
分析:
在项目管理中,(73)是一个包含了开始和结束时间的里程碑、活动和可交付物的列表。其内容通常在考虑了活动的联系和时间安排的基础上,依据资源的(74)、预算和持续时间估计得到。
(73)A、进度表 B、活动 C、计划 D、承包商
(74)A、寻找 B、平衡 C、分配 D、分布
参考答案:(73)A、(74)C