All of followings should be done by the project manager during project control except (74).
A. Determine that a change has occurred
B. Ensure that a change is agreed
C. Make sure all changes are approved by management
D. Manage changes as they occur
分析:
下列中,(74)不是项目经理在项目控制过程中要完成的工作。
A、确定变更已经发生
B、确保变更被同意
C、确保所有变更均被管理人员批准
D、变更发生是对其进行管理
参考答案:B、C