73、Project manager believes that modifying the project scope may provide added value for the customer . The project manager should ____.
(73) A、change the scope baseline
B、contact the customer to determine if the change adds value
C、call a meeting of the change control board
D、change the project’s objectives
分析:
项目经理相信调整范围能为客户增加收益,项目经理应该(73)。
A:改变范围基线、B:联系客户确定变更是否增加收益、C:召开变更控制委员会会议、D:改变项目目标。
参考答案:C