The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .
A.measure, delay, record, distribute, analyze, and direct
B.plan, schedule, monitor, control, report, and forecast
C.promote, highlight, monitor, control, forecast, and report
D.emphasize, visualize, analyze, conceptualize, report, and record
【正确答案】B