74、A critical path for a project is the series of activities that determine( )by which the project can be completed.
A、the earliest time B、the latest time
C、the total time D、the free time
尚大教育-分析:
关键路径通常由一系列决定项目工期的活动组成,它们决定了整个项目的最早完成时间。
尚大教育-参考答案:A