【英语专题】【1505信监】试题74What does a CPI
来源: 作者: 时间;2017-11-01 11:46:57 点击数: 尚大软考交流群:376154208
【1505信监】试题7474、What does a CPI of 80% mean?( ).A、As of now we expect the total project cost of 80% more than planned
B、When the project is completed, we will have spent 80% more
C、Your project is only progressing at 80% of that planned
D、Your
<尚大教育,教育至上,人才为大:sdedu.cc>

 

1505信监】试题74

74、What does a CPI of 80% mean?(  ).

A、As of now we expect the total project cost of 80% more  than planned
B、When the project is completed, we will have spent 80% more
C、Your project is only progressing at 80% of that planned   
D、Your project is only getting 80 cents out of every RMB invested

尚大教育-分析

A目前我们预计比原计划多出80%的项目总成本

B当项目完成后,我们会多花费80

C、项目进度是只在80%的计划进度

D、项目只获得80美分每支出人民币1

尚大教育-参考答案D

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:【英语专题】【1505信监】试题73( )is the budgeted amount
下一篇:【英语专题】【1505信监】试题75
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章