【英语专题】【1511信监】试题74 During planning you sit down
来源: 作者: 时间;2017-11-01 11:39:19 点击数: 尚大软考交流群:376154208
【1511信监】试题7474、During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario?A、The team did not creat
<尚大教育,教育至上,人才为大:sdedu.cc>

 

1511信监】试题74

74、During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate. This duration is what you commit to complete the project. What is wrong with the scenario?

A、The team did not create the estimate and estimating tales too long using that method
B、The team did not create the estimate and a network diagram was not used
C、The estimate is too long and should be created by management   
D、The project estimate should be the same as the customer's required completion date

尚大教育-分析

当你打算坐下来评估每个任务所需的时间和总共的项目评估。在你提交完成项目估算的这个期间。依据以上场景错误的选项是?

A.团队使用这种方法并没有产生太长时间的估计和估计故事。

B.团队不需要创建估算,不需要用到网络图。

C.估计太长了,应该由管理人员来制定。

D.项目估算应与客户要求的完工日期相同。

尚大教育-参考答案B

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:【英语专题】【1511信监】试题73 If IP address is 202.130.191.33
下一篇:【英语专题】【1511信监】试题75A software requirements specification is tha
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章