74、In all projects,needs must be tempered by schedule ,cost and resource constraints. Project success depends primarily on( ).
A、The quality of the schedule and cost control analysis
B、Customer satisfactions
C、Customer compromises in defining its needs
D、Exceeding customer requirements through gold-plating
尚大教育-分析:
在所有的项目中,需求会受到进度、成本和资源方面的约束。项目的成功取决于客户的满意度。
尚大教育-参考答案:B