(70)A.28
B.31
C.33
D.34 ●Define Activities is the process of identifying the specific actions to be performed to produce the __(71)__.
(71)A.project elements
B.work drafts
C.work package
D.project deliverables ●Project work packages are typically d
<尚大教育,教育至上,人才为大:sdedu.cc>

(70)A.28
B.31
C.33
D.34

 

●Define Activities is the process of identifying the specific actions to be performed to produce the __(71)__.
(71)A.project elements
B.work drafts
C.work package
D.project deliverables

 

●Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for __(72)__,scheduling,executing,and monitoring and controlling the project work.
(72)A.reviewing
B.estimating
C.auditing
D.expecting

 

●The Estimate Activity Resource process is closely coordinated with the __(73)__ process.
(73)A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements

 

●Estimating activity durations uses information on activity scope of __(74)__,required resource types,estimated resource quantities,and resource calendars.
(74)A.milestone
B.baseline
C.quality
D.work

 

●Developing the project schedule is often an iterative process.It determines the planned start and finish dates for project activities and milestones.Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to __(75)__ progress.
(75)A.analyze
B.track
C.level
D.extend

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2009上半年信息系统项目管理师考试下午真题--案例分析 (三)
下一篇:2008年下半年信息系统项目管理师下午论文--试题一 论项目的采购管理
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章