试题71-命-技-N.ZJ.00.p000-9.00-71、After acceptance and formal transfer of information systems to customers it has entered the stage of ()
A、preparation
B、operation and maintenance
C、development
D、extinction试题72-命-技-N.ZJ.00.p000-9.00-72、()a method of obta
<尚大教育,教育至上,人才为大:sdedu.cc>
试题71-命-技-N.ZJ.00.p000-9.00-
71、After acceptance and formal transfer of information systems to customers it has entered the stage of ()
A、preparation
B、operation and maintenance
C、development
D、extinction
试题72-命-技-N.ZJ.00.p000-9.00-
72、()a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it
A、prototype
B、object oriented
C、structured method
D、iterative method
试题73-命-技-N.ZJ.00.p000-9.00-
73、The scope management plan is how the team will prepare the (), a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A、project charter B、project scope goal
C、project budget D、project scope statement
试题74-命-技-N.ZJ.00.p000-9.00-
74、( ) is one of the tools and techniques of Sequence Activities
A、Decomposition
B、Fishbone Diagram
C、Precedence Diagramming Method
D、Expert Judgment
试题75-命-技-N.ZJ.00.p000-9.00-
75、The schedule management plan is a component of the project management plan. The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the () of the project, and includes appropriate control thresholds.
A、goals B、values C、needs D、level