试题71-命-技-N.ZJ.00.p000-9.00-71、In an Information system. The( ) is the bridge between hardware and people
A、keyboard B、internet C、disk D、data试题72-命-技-N.ZJ.00.p000-9.00-72、Cloud-computing providers offer their “services” according to dif
<尚大教育,教育至上,人才为大:sdedu.cc>
试题71-命-技-N.ZJ.00.p000-9.00-
71、In an Information system. The( ) is the bridge between hardware and people
A、keyboard B、internet C、disk D、data
试题72-命-技-N.ZJ.00.p000-9.00-
72、Cloud-computing providers offer their “services” according to different models, which happen to form a stack( ), platform as a service (Paas), software as a service (SaaS)
A、hardware as a service (Haas)
B、network as a service (NaaS)
C、infrastructure as a service (IaaS)
D、data as a service (DaaS)
试题73-命-技-N.ZJ.00.p000-9.00-
73、( )estimating is a technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project.
A、Parametric B、Analogous
C、Three-point D、Expert judgment
试题74-命-技-N.ZJ.00.p000-9.00-
74、Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
A、fast tracking B、what-if scenario analysis
C、resource leveling D、critical chain method
试题75-命-技-N.ZJ.00.p000-9.00-
75、If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan are revised and reissued to reflect the approved changes
A、developing baselines B、testing baselines
C、schedule baselines D、ending baselines