登录   |   注册
    准考证打印   论文投票   报考指南   论文辅导   软考培训   郑重申明  
您现在的位置:  首页 > 软考学苑 > 软考历年真题 > 信息系统项目管理师-真题 >> 正文
正文
2010年下半年 信息系统项目管理师 上午试题(71-75)
来源:尚大教育 作者:尚大教育 时间;2018-12-05 14:43:02 点击数: 尚大软考交流群:376154208
试题71-命-技-N.ZJ.00.p000-9.00-时间管理.过程名称● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
A.activity duration estimating, schedule developing, acti
<尚大教育,教育至上,人才为大:sdedu.cc>

试题71-命-技-N.ZJ.00.p000-9.00-时间管理.过程名称

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
 
 

试题72-命-技-N.ZJ.00.p000-9.00-关键链法

● Many useful tools and techniques are used in developing schedule. (72)  is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A.PERT                    B.Resource levelling
C.Schedule compression       D.Critical chain method
 

试题73-命-技-N.ZJ.00.p000-9.00-CCB

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
A.executive IT manager        B.project manger
C.change control board         D.project sponsor
 
 

试题74-命-技-N.ZJ.00.p000-9.00-版本控制工具

● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74)  is not a project configuration management tool.
A.Rational Clearcase B.Quality Function Deployment
C.Visual SourceSafe D.Concurrent Versions System
 
 

试题75-命-技-N.ZJ.00.p000-9.00-WBS.工作包

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the  (75)  level.
A.independent resource       B.individual work load
C.work milestone            D.work package
 
<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2010年下半年 信息系统项目管理师 上午试题(61-70)
下一篇:2010年下半年 信息系统项目管理师 下午真题--【大汇总】
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章