●Project Quality Management processes include all the activities of the __(71)__ that determine quality policies,objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)A.project
B.project management team
C.performing organization
D.customer
●The project team members should also be aware of one of the fundamental tenets of modern quality management:quality is planned,designed and built in,not __(72)__.
(72)A.executed in
B.inspected in
C.check-in
D.look-in
●The project __(73)__ is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria.
(73)A.work performance information
B.scope statement
C.change requests
D.process analysis
●Performing __(74)__ involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
(74)A.quality planning
B.quality assurance
C.quality performance
D.quality control
●__(75)__ involves using mathematical techniques to forecast future outcomes based on historical results.
(75)A.Trend analysis
B.Quality audit
C.Defect repair review
D.Flowcharting