2007下半年信息系统项目管理师考试真题(综合知识71-75)
来源:尚大教育 作者:尚大教育 时间;2018-12-05 10:30:40 点击数: 尚大软考交流群:376154208
●Project Quality Management processes include all the activities of the __(71)__ that determine quality policies,objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)A.project
B.project management t
<尚大教育,教育至上,人才为大:sdedu.cc>

●Project Quality Management processes include all the activities of the __(71)__ that determine quality policies,objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)A.project
B.project management team
C.performing organization
D.customer

 

●The project team members should also be aware of one of the fundamental tenets of modern quality management:quality is planned,designed and built in,not __(72)__.
(72)A.executed in
B.inspected in
C.check-in
D.look-in

 

●The project __(73)__ is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria.
(73)A.work performance information
B.scope statement
C.change requests
D.process analysis

 

●Performing __(74)__ involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
(74)A.quality planning
B.quality assurance
C.quality performance
D.quality control

 

●__(75)__ involves using mathematical techniques to forecast future outcomes based on historical results.
(75)A.Trend analysis
B.Quality audit
C.Defect repair review
D.Flowcharting

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2007下半年信息系统项目管理师考试真题(综合知识61-70)
下一篇:2007下半年信息系统项目管理师考试真题(案例分析)--大汇总
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章