●In approximating costs,the estimator considers the possible causes of variation of the cost estimates,including __(71)__.
(71)A.budget
B.plan
C.risk
D.contract ●Project Quality Management must address the management of the project and the __(72)__ of
<尚大教育,教育至上,人才为大:sdedu.cc>

●In approximating costs,the estimator considers the possible causes of variation of the cost estimates,including __(71)__.
(71)A.budget
B.plan
C.risk
D.contract

 

●Project Quality Management must address the management of the project and the __(72)__ of the project.While Project Quality Management applies to all projects,regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.
(72)A.performance
B.process
C.product
D.object

 

●__(73)__ is a category assigned to products or services having the same functional use but different technical characteristics.It is not same as quality.
(73)A.Problem
B.Grade
C.Risk
D.Defect

 

●Project __(74)__ Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation,collection,distribution,storage,retrieval,and ultimate disposition of project information.
(74)A.Integration
B.Time
C.Planning
D.Communication

 

●The __(75)__ process analyzes the effect of risk events and assigns a numerical rating to those risks.
(75)A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2006下半年信息系统项目管理师考试真题(综合知识61-70)
下一篇:2006下半年信息系统项目管理师考试真题(案例分析)--汇总
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章