71、()is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cogn
<尚大教育,教育至上,人才为大:sdedu.cc>

71、()is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cognittive computing) or replacing peopleon execution ofnonroutine tasks.

A、Cloud service

B、Blockchain

C、Internet of things

D、Artificial intellingence

72、()is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion  of the network.

A、Cloud service

B、Blockchain

C、Internet of things

D、Artificial intellingence

73、includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . managing the project scope is primarily concerned with defining and controlling what is not included in the project.

A、Create scope

B、Project stakeholder management

C、Preject scope management

D、Project cost management

74、Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

A、expert judgment

B、analogous estimating

C、requirements traceability matrix

D、three-point estimating

75、The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

A、Manage quality

B、Quality audit

C、Quality metrics

D、Quality improvement

<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2005上半年信息系统项目管理师考试真题(论文)--【大汇总】
下一篇:2005下半年信息系统项目管理师考试真题(综合知识1-10)
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章