● Project__(71)__is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality
(71)A.risk
B.problem
C.result
D.data
● Categories of risk response are __(72)__
(72)A.Identification, quantification, response development, and response control
B.Marketing technical, financial, and human
C.Avoidance, retention, control, and deflection
D.Avoidance, mitigation, acceptance, and Transferring
● __(73)__is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
(73)A.Quality assurance (QA)
B.Quality planning
C.Quality control (QC)
D.Quality costs
● __(74)__is primarily concerned with defining and concerning what is and is not included in the project.
(74)A.Project Time Management
B.Project Cost Management
C.Project Scope Management
D.Project Communications Management
● A project manager believes that modifying the scope of the project may provide added value service for the customer .The project manager should__(75)__
(75)A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline