(71) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.
A. Integrated management
B. Configuration management
C. Scope management
D. Requirements management
分析:
(71)是一个过程,该过程用来对需求进行记录、分析、跟踪、优先级排序并确认、然后进行变更控制并与干系人联系。它是一个贯穿于项目始终的连续过程。
A. 整体管理
B. 配置管理
C. 范围管理
D. 需求管理
参考答案:D