试题75-命-技-N.ZJ.00.p000-9.00-WBS.工作包● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level. A.independent resource B.individual work load C.work milestone
<尚大教育,教育至上,人才为大:sdedu.cc>
试题75-命-技-N.ZJ.00.p000-9.00-WBS.工作包
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
A.independent resource B.individual work load
C.work milestone D.work package
C类(75)D ……直到分解到“工作包”为止
<尚大教育,教育至上,人才为大:sdedu.cc>